Thank you for reading! I hope this helps. So for the above example instead of entering 21days as the duration of the task, you would enter 294hrs (21*14 =294).
#Adte projectlibre how to
So how to you dodge this curveball? Well there are essentially 2 options – The project can be given a name, the name of project manager, start date (it. Indicates that the finish date of the predecessor task determines the. ProjectLibre: An Open Source Alternative to Microsoft Project ProjectLibre. This is the reason why the dates do not match the duration of the task. The following table describes the four possible task relationships. Now since we have a task calendar assigned to this task that is 14hrs a day with no holidays, Microsoft Project spreads these 168hrs over 14hrs a day which comes out to 12days (168/14 = 12).

Project goes ahead and converts the 21 days into 168hrs (21*8 = 168hrs). So let’s say you enter a task duration of 21 days.
#Adte projectlibre professional
So I opened the project in Microsoft Project Professional and went to File -> Options –> ScheduleĪs seen above, Microsoft Project uses these setting to convert days to hours. We added 5 new languages and now are translated into 29 languages. Works fine for a few tasks (up to around 40 in my repeated experience with several projects) and then arbitrarily resets dates to the date the overall project. The next step was to check the Project options – ProjectLibre 1.9.3 now has an automated way to change languages and country profiles. On further investigation, I noticed the task calendar assigned to this task was a 14hrs a day shift with no holidays. The only thing different is that I have a task calendar assigned to this task.” Few days ago one of our client called me and said “There seems to be a bug in Microsoft Project, it is unable to calculate the correct finish date for one of my tasks.” He further added saying “I do not have any constrains or resources assigned to this task yet, but, if I manually calculate the end date for this task, I get a finish date ‘X’, but Microsoft Project is providing ‘Y’ as the end date for this task. LSU rev1FEB2021 L24.